Basements - Case Study : Basement For Vehicles

Scope of Works:

Construction of two basements partially beneath existing two storey detached homes in sandy ground. One for the installation of a ramped car park the other for gym and cinema installation.

Basement Construction
Design Basement Design
Phase 1 – Installation of contiguous piled retaining walls temporary cased through sand and temporary stooling of existing buildings.

In order to safely undertake the excavation of the basements it was necessary for the existing buildings to be supported. In order to achieve this the properties were underpinned by piled reinforced concrete rafts transferring the load of the structure onto a perimeter contiguous piled wall and internal temporary support piles.

Contiguous piled retaining walls
Steel reinforcement for up stand nib fixed and basement roof soffit installation in progress. Steel reinforcement
Basement soffit slab bottom steel fixed, light well shutter and slab side shutters fixed. Basement soffit
Completed steel reinforcement fixing for ground level slab. Note the propped walls of the existing building. Steel reinforcement fixing for ground level slab
Completed top slab supporting existing building onto temporary internal piles and perimeter contiguous piled wall. Contigous piled wall
Phase 2 - Excavation of basement.

Completed basement excavation note the exposed line of contiguous piles and ground level light well.

Basement excavation
Basement excavation completed, perimeter contiguous piled retaining wall exposed and blinding installed. Note the internal temporary piles supporting the ground level slab and existing property above. Temporary supportin piles
Phase 3 – Installation of basement reinforced concrete slab.

Basement steel reinforcement fixing in progress, bottom mat completed.

Basement steel reinforcement fixing
Ramp access to basement steel reinforcement fixed including flank up stand lining walls. Ramp access to basement
Completed access ramp, ground floor down stand beam spreading load form ground level to brickwork piers. Completed basement ramp access
Completed basement floor slab and ramp. Note the steel reinforcement fixed to the contiguous piled wall in preparation for lining wall concrete installation. Basement floor slab and ramp
The completed basement ramp access. Basement ramp access conpleted

Phase 4 – Installation of concrete lining walls and waterproofing measures.

Exposed contiguous piled wall lined with reinforced concrete. Permanent load bearing walls under construction. Once the permanent load bearing walls are installed the temporary internal support piles can be removed.

Concrete lining walls
Completed wall waterproof lining. Wall waterproof lining.