Scope of Works:Construction of two basements partially beneath existing two storey detached homes in sandy ground. One for the installation of a ramped car park the other for gym and cinema installation. |
![]() |
| Design | ![]() |
| Phase 1 – Installation of contiguous piled retaining walls temporary cased through sand and temporary stooling of existing buildings.
In order to safely undertake the excavation of the basements it was necessary for the existing buildings to be supported. In order to achieve this the properties were underpinned by piled reinforced concrete rafts transferring the load of the structure onto a perimeter contiguous piled wall and internal temporary support piles. |
![]() |
| Steel reinforcement for up stand nib fixed and basement roof soffit installation in progress. | ![]() |
| Basement soffit slab bottom steel fixed, light well shutter and slab side shutters fixed. | ![]() |
| Completed steel reinforcement fixing for ground level slab. Note the propped walls of the existing building. | ![]() |
| Completed top slab supporting existing building onto temporary internal piles and perimeter contiguous piled wall. | ![]() |
| Phase 2 - Excavation of basement.
Completed basement excavation note the exposed line of contiguous piles and ground level light well. |
![]() |
| Basement excavation completed, perimeter contiguous piled retaining wall exposed and blinding installed. Note the internal temporary piles supporting the ground level slab and existing property above. | ![]() |
| Phase 3 – Installation of basement reinforced concrete slab.
Basement steel reinforcement fixing in progress, bottom mat completed. |
![]() |
| Ramp access to basement steel reinforcement fixed including flank up stand lining walls. | ![]() |
| Completed access ramp, ground floor down stand beam spreading load form ground level to brickwork piers. | ![]() |
| Completed basement floor slab and ramp. Note the steel reinforcement fixed to the contiguous piled wall in preparation for lining wall concrete installation. | ![]() |
| The completed basement ramp access. | ![]() |
|
Phase 4 – Installation of concrete lining walls and waterproofing measures. Exposed contiguous piled wall lined with reinforced concrete. Permanent load bearing walls under construction. Once the permanent load bearing walls are installed the temporary internal support piles can be removed. |
![]() |
| Completed wall waterproof lining. | ![]() |