Housedeck Developer - Construction Sequence

Construction Sequence Larger Rigs

1. Piling rigs appropriate to the site restrictions are used to install bored, driven or augered piles individually designed dependent on soil conditions and structure loading.

2. 50mm concrete working surface is installed.

3. If required, a void is created after pile installation using our patented Deck Support Units (DSU’s) to allow for ground heave or gas ventilation. This eliminates the need for void formers or other anti-heave precautions.

4. Advanced in-house flat slab software allows the maximisation of steel efficiency and the minimisation of costs.

5. Our unique stainless steel angle is used as formwork for the slab and provides a clean, flat and level working surface for bricklaying or timber frame installers to start immediately.

6. Concrete is poured and floated to an extremely high tolerance.