Crown Cottages

Windsor, Berkshire

Value: £97,000
Duration: 13 weeks
Client: K & H Construction

 

By recommendation, we were asked to provide an underpinning scheme for these two grade II listed cottages on the Crown Estate in Windsor.

These cottages had previously been repaired with masonry reinforcement, however, due to the shallow nature of existing foundations, the clay subsoil and adjacent vegetation, the movement persisted.

Due to this continued movement, a piled raft was required. This entailed the removal of the existing floor, reduced level dig and temporary works to support the superstructure. All of which allowed us to install a piled raft under the entirety of the original structure.

  • Temporary Works

Uncommon for turn of the century properties, these cottages were built with cavity walls. This did not become a commonplace architectural feature until after the war. Adding to this increased width, these cavity walls also feature an external plinth. This meant the external walls of the primary structure were much wider than is traditionally seen and required additional support. Customarily, we would only need to install one stool per position, instead, our engineers designed a double stooling scheme in these areas. This involves two stools being installed adjacently, to prevent any risk of collapse to the superstructure or external plinths.

  • Piled Raft Design

Our engineers designed a 300mm uniformly thick slab on 16m deep piles of 250mm diameters. Due to the clay subsoil and mature vegetation so close to the properties, 160mm of Clayboard was allowed for under the slab as an anti-heave precaution.

One of the main challenges of this project for our engineers was the rear projection. Due to the exceptionally narrow design, access was limited and the end rooms were not wide enough for our mini- rigs to operate once through the door. To tackle this our engineers extended the raft to the exterior of the building, with piles supporting from outside the superstructure. This avoided any internal walls needing to be demolished to allow for the rig, allowing our client to maintain the properties to the utmost degree.

 

For expert advice and bespoke pricing

Call 01442 212112 Email us

Newsletter signup

* indicates required

By signing up, you agree to our Privacy Policy and Terms & Conditions.