Fulham School

London

Value: £741,000

Size: 1400m2 (over two sites)

Duration: 36 weeks

Scope of work:

  • We worked with closely Morgan Sindall on this this two plot site, divided between the girls and boys schools, to install our Comdeck system.

  • One challenge with this project was the required noise and vibration reduction, due to construction taking place during the exam period. By changing the sequence and method we managed to eliminate the heavy-duty breakers, floor saws and the requirement for pile cropping.

  • In total we installed 322, 300mm dia. CFA piles, not exceeding 15m. We also installed holding down bolts and under slab drainage.

  • By using the Comdeck system we greatly reduced the spoil removal, eradicating the need to excavate and form ground beams, in turn reducing the concrete required. This also reduced the amount of vehicle and plant movement associated with the excavation, spoil removal, and concrete. Reducing the overall carbon footprint of the site.

For expert advice and bespoke pricing

Call 01442 212112 Email us

Check out our recently completed projects

Newsletter signup

* indicates required

By signing up, you agree to our Privacy Policy and Terms & Conditions.