Nottinghill Methodist Church

Nottinghill Methodist Church

Nottinghill, London

Value: Circa £115K

Size: Varies

Duration: 12 weeks

Scope of work : 

    • This project consisted of mass concrete underpinning to an existing basement structure for a medieval church in Notting Hill
    • Design of innovative temporary works to support existing church structure whilst underpinning works were completed
    • Design of temporary shoring system
    • Demolition and removal of existing floor structure
    • Removal of existing foundations where required and reduced dig to formation
    • Installation of temporary works
    • Traditional mass concrete underpinning works to main basement area and under existing staircase to main steeple structure
    • Removal of temporary works where required
    • Dry pack installation
    • ASUC guarantee

Download PDF Version: Click Here

North Lodge

North Lodge

Chilham Castle Estate, Chilham, Canterbury, Kent

Value: Circa £50K

Size: 70m2

Duration: 8 weeks

Scope of work : 

    • This project was to stabilise an existing lodge house suffering from subsidence within the curtilage of an existing grade 1 listed estate
    • Underpinning piled raft slab to a grade I listed lodge house – 70m2
    • Demolition and removal of existing floor structure
    • Temporary works
    • Demolition of existing foundations and reduced dig to formation
    • Restricted access mini piling works
    • Construction of voided raft underpinning slab
    • Removal of temporary works
    • ASUC Guarantee

Download PDF Version: Click Here

Leybourne Manor Estate

Leybourne Manor Estate

Leybourne, West Mailing, Kent

Value: Circa £730K

Size: Varies

Duration: 40 weeks

Scope of work : 

  • This project consisted of a range of different underpinning techniques to several areas of existing grade 1 & grade 2 listed properties within a new build site for a national house builder
  • Underpinning piled raft slab and piled raft slab to an existing clock tower building – 421m2
  • Design of innovative temporary works to support existing structure and 5 storey clock house tower demolition and removal of existing floor structure
  • Demolition of existing foundations and reduced dig to formation
  • Restricted access mini piling works
  • Construction of voided raft underpinning slab
  • Removal of temporary works
  • Traditional mass concrete underpinning
  • Cantilever pile and beam underpinning
  • Underpinning piled raft slab to an existing single storey
    Manor House building – 540m2
  • Housedeck Slab to 6 new build properties – 505m2
  • ASUC guarantee

Download PDF Version: Click Here

Gatwick Airport

Gatwick Airport

Baggage Reclaim (South Terminal)

Value: £50,000

Duration: 9 days

Rig: Klemm 709

Scope of work : 

  • Restricted Access Piling with an overall height restriction of 10.5m due to nearby buildings on site, and the airport radar system
  • Complete in-house bespoke design and value engineered scheme
  • We installed 15no 450mm diameter piles up to a depth of 14m with airside restrictions
  • Piling carried out between critical airport live services

Download PDF Version: Click Here

Hill Street

Hill Street

London

Value: Over £1 million

Size: 107m2

Duration: 35 weeks

Scope of work : 

  • Two storey basement constructed in a top down sequence
  • Contiguous bored pile wall installed close to the adjoining party wall- designed by Abbey Pynford
  • Reinforced concrete works including Basement slab, composite lining walls and ground floor soffit slab
  • Below slab drainage
  • Water resisting concrete additives
  • ASUC guarantee

Download PDF Version: Click Here

Big Yellow Storage

Big Yellow Storage

Camberwell

Value: £300,000

Duration: 26 days

Rig: Geax EK75

Scope of work : 

  • Complete in-house bespoke design and value engineered scheme
  • We installed 367 piles in total. A Contiguous bored pile wall was installed to allow for the basement excavation which was designed to be fully cantilevered in the temporary condition – reducing overall costs and dig-out duration & eliminating the use of temporary propping
  • Bearing piles were installed including bearing piles to support the tower crane base
  • As the site location was close to residential properties, vibration monitoring was carried.

Download PDF Version: Click Here

School in Balham

School in Balham

London

Value: £500,000

Size: 167m2

Duration: 34 weeks

Scope of work : 

  • Single storey basement constructed partly beneath an existing school building
  • Top down construction sequence to maximise the full utilisation of the school’s playground
  • Installation of transfer ground floor slab supported on temporary structural steel work design by Abbey Pynford
  • Excavation & completion of basement structure
  • Specialist concrete finish to suit architectural requirements
  • Restricted Access Piling for the construction of king post retaining wall – designed by Abbey Pynford
  • Water resisting concrete additives
  • This project was completed 3 weeks ahead of the program, saving costs and time

Download PDF Version: Click Here

Underpinning a 5 storey Apartment in London

Underpinning a 5 storey Apartment in London

Value: £500k<

Size: Over 400m2

Duration: 36 weeks

Scope of work : 

  • Full design and build underpinning scheme
  • Demolition and Construction of reinforced concrete retain wall on an integral part of underpinning scheme
  • Pile raft underpinning scheme for 2 large mansion blocks including a large existing chimney cantilevering from the rear elevation

Download PDF Version: Click Here (Coming Soon)

Piled Raft Underpinning to 3 Blocks in North West London

Piled Raft Underpinning to 3 Blocks in North West London

Value: £300k<

Size: 500m2

Duration: 18 weeks

Scope of work : 

  • Full underpinning scheme design
  • Demolition and removal of existing floor structure
  • Temporary works and demolition of earth retaining walls
  • Restricted access mini piling
  • Construction of voided raft underpinning slab
  • Construction of reinforced concrete retaining wall
  • Removal of temporary works
  • ASUC Guarantee

Download PDF Version: Click Here (Coming Soon)

Design and Build Pile Raft underpinning for a large Victorian Semidetached Villa

Design and Build Pile Raft underpinning for a large Victorian Semidetached Villa

Value: £125k<

Size: 115m2

Duration: 16 weeks

Scope of work : Pile raft underpinning design and build solution

Download PDF Version: Click Here (Coming Soon)