Big Yellow Storage

Camberwell

Value: £300,000

Duration: 26 days

Rig: Geax EK75

Scope of work : 

  • Complete in-house bespoke design and value engineered scheme
  • We installed 367 piles in total. A Contiguous bored pile wall was installed to allow for the basement excavation which was designed to be fully cantilevered in the temporary condition – reducing overall costs and dig-out duration & eliminating the use of temporary propping
  • Bearing piles were installed including bearing piles to support the tower crane base
  • As the site location was close to residential properties, vibration monitoring was carried.