Value: £60,000

Size: 135m2

Duration: 6 weeks

Rig: Klemm 709

Scope of work : 

    • Suspended raft designed in-house
    • Setting out of foundation works
    • On site supervision of works (Working foreman & visiting Engineer)
    • 50mm concrete working surface acting as a stable, weatherproof base for the formwork
    • 300mm Dia CFA piles not exceeding 10.5m in length to our design (F.O.S = 3.0)
    • 300x300mm Columns to Support Structural Slab
    • 1No. Voided Housedeck structural slab (135m2)
    • 1.2m void to underside of Housedeck slab to accommodate flood risk
    • Straight edge detail with 15mm chamfer at the top and bottom of the suspended slab
    • Under slab drainage and services