Open site Basement adjoining sensitive structures in Marylebone

Value: £1m>

Size: 210m2

Duration: 34 weeks

Scope of work :

  • Full design with finite element analysis
  • Installation of penetration Board Pile Wall
  • Reduced level of excavation and trimming of existing foundation
  • Temporary propping
  • Below slab drainage and sumps
  • Reinforcement concrete works including Basement slab, composite lining walls and ground floor soffit slab
  • Water resisting concrete additives
  • ASUC guarantee
  • All undertaken through restricted access archway