Wendover Woods Visitor Centre

Wendover, Buckinghamshire

Value: £227,000

Size: 634m2

Duration: 10 weeks

Scope of work : 

    • Full in-house pile and slab design
    • Installation of 722m2 50mm concrete working surface
    • Installation of 79No; 250mm Ø CFA bearing piles with a FoS=2.5
    • Installation of the clients foul and Storm drainage system; including all service and utility ducting
    • Construction and Installation of 225mm thick reinforced structural concrete Comdeck slab with 180mm void
    • Installation of 84 sets of bolts for the client’s steel frame supports
    • Our original scope of work was to provide a piled raft foundation with a 180mm
      void for the tree roots and potential heave associated with the soil condition
    • The piles were installed using one of our Klemm 709’s with a 7.5m3 agitator. Piling
      was completed in 5 days with no problems
    • The Comdeck slab installation went very smoothly, incorporating our pre-formed
      speed shutter. The whole deck was completed ready for a pour within 7 days
    • Abbey Pynford worked with Kier to produce a high quality product, safely, on budget, and on program. We also provided drone and time lapse cameras for the clients progress reports